JPR Environmental installed spiling up to a metre in height and fixed each stake with a tie back to the recently built wall. We supervised the backfilling and excavation of the inlet to create a natural and highly attractive landscaping feature on this executive development.
We were asked to return the following year to install 10m of additional spiling around an outlet into the river adjoining the site.

Spiling and inlet following landscaping.

Willow spiling in the autumn following installation

Additional willow spiling on outflow at edge of site
|